Question: Critical Path is _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Critical Path is ________________________________________ with a duration of ____________________ days.
Draw the PERT diagram Given
Activity Predecessor Duration (days)
A --3
B A 4
C A 2
D B 5
E C 4
F D, E 2
Use forward and backward pass to determine critical path and duration for the above project based on your PERT Diagram
ES Activity EF
LS Duration LF
Early Start /Early Finish
Late Start / Late Finish