Question: draw the project network using the AOA and AON representations A project comprises 10 activities with the following precedence relations and dura- tion estimates (in

draw the project network using the AOA and AON

draw the project network using the AOA and AON representations

A project comprises 10 activities with the following precedence relations and dura- tion estimates (in days): Activity A B D E Duration in weeks) Predecessor Optimistic Nost Likely Pessimistie 2 3 A 1 2 A 2 10 1 3 1 15 B 2 1 3 7 1.5 F. H 1 2 1.5 1 2 Oo oo --- - G. H I J 1