Question: Draw the schedule network diagram for a Ben Stillwells scientific project showing ES, EF, LS, LF & Slack using the information provided in the table
Draw the schedule network diagram for a Ben Stillwells scientific project showing ES, EF, LS, LF & Slack using the information provided in the table below. (15 marks) Activity Duration / days Dependency START 0 - A-Formulate project concept 3 Start B-Obtain approval 2 Start C-Perform detail planning 10 A D-Gather plant samples 4 B,C E-Test plant samples 4 D F-Audit and verify test results 5 E G-Prepare project report 7 E,F H- Present report to Manager 1 G END 0 H b. Determine the critical path of the project and float of activity B? (2 marks) c. In order to expedite the execution of the project Ben has decided to crash the activities below. Calculate the maximum crash day and cost crash days. (6 marks)