Question: 1) Critical Path Method Below is information about a project to implement a new manufacturing cell to assemble personal digital assistant devices Activity Duration Predecessors

1) Critical Path Method

Below is information about a project to implement a new manufacturing cell to assemble personal digital assistant devices

Activity

Duration

Predecessors

ES

EF

LS

LF

Total Slack

  1. Design process requirements

2

-

  1. Benchmark competitors processes

4

A

  1. Prepare benchmark report

1

B

  1. Design process and layout

2

A

  1. Finalize design and set up manufacturing cell

2

C,D

  1. Select and train operators

1

D

  1. Pilot test new process

2

E,F

  1. Finalize process design

1

G

  • Draw a network diagram here.

Place your response here

  • Identify the ES, EF, LS, LF and slack times in the table using the critical path method. (You may fill in the table above)

  • During the initial stages of the project, a new set of requirements were discovered that would extend the process and layout design activity from 2 to 6 months. The operations group which initiated these requirement changes argues that they would not impact the project duration. Is this true? Justify your answer.

Please include pictures, thank you!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!