Question: Draw up a Chase Demand Production plan based on the following information Quarter Sales Forecast Spring 70,000 tubes Summer 45,000 tubes Autumn 80,000 tubes Winter
Draw up a Chase Demand Production plan based on the following information
Quarter Sales Forecast
Spring 70,000 tubes
Summer 45,000 tubes
Autumn 80,000 tubes
Winter 250,000 tubes
Hiring Cost = 200 per worker
Firing Cost = 500 per worker
Stock cost = 0.50 per tube per quarter
Shortage cost = 3.00 per tube per quarter
Production cost = 2.00 per tube
Production per employee: 1000 tubes per quarter
Workforce at start: 100 employees
Effective capacity: 150,000 tubes per quarter
Step by Step Solution
There are 3 Steps involved in it