Question: Drop Down Choice for A. - Workstation A - Workstation B - Workstation C - Workstation D Drop Down Choice C. First Blank - Yes

Drop Down Choice for A. - Workstation A - Workstation B - Workstation C - Workstation D
Drop Down Choice C. First Blank - Yes - No Third Blank - Lower - Higher
Drop Down Choice for D. - Workstation A - Workstation B - Workstation C - Workstation D
Jefferson Manufacturing machines parts for assembly in air compressors. The process is shown below. Workstation A 25 minutes/part Workstation C 25 minutes/part Workstation D 40 minutes part Workstation B 15 minutes/part a. Where is the bottleneck workstation? Round your answer to two decimal places. The bottleneck is -Select- with the throughput rate of parts/hour. b. What is the longest throughput time for the entire work cell? Round your answer to the nearest whole number. minutes C. If Jefferson Manufacturing works a 40-hour week, can this production cell meet a demand of 75 parts/week? Do not round intermediate calculations. Round your answer to the nearest whole number -Select- since the bottleneck workstation throughput rate of parts/week is -Select- v than the demand. d. Where should the operations manager spend his or her firm's improvement funds? At -Select- VStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts