Question: dropdown box que ons. Choose the correct answer from each Consider the following project (assume that normal and crash times are in days): Activity Immediate

dropdown box que ons. Choose the correct answer
dropdown box que ons. Choose the correct answer
dropdown box que ons. Choose the correct answer from each Consider the following project (assume that normal and crash times are in days): Activity Immediate Normal Time Normal Cost Crash Time Crash Cost Predecessors (NT) (NC) (CC) (CT) Slope 7 $4.200 5 $5.400 B A 5 $1,800 3 $2.400 B 4 $2,250 2 $2,500 D 8 $900 5 $1.200 E CD 4 $1.000 4 $1,000 1. What is the total cost required to complete the project on normal time? $ 10,150 2. Which of the following activities is not critical? C 3. The slopes of activities A and D are: 600 and 300, respectively 4. The most cost-effective schedule to reduce the project duration by 1 day is: Crash activities B and D 1 day 5. The most cost-effective schedule to reduce the project duration by another day is: Crash activity C 1 day at a tot 6. The shortest possible (i.e., minimum) project duration in days is: 15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!