Question: dropdown box. questions. Choose the correct answer from each Consider the following project. Assume that all activities have the same non-zero slopes. Immediate Activity Normal

dropdown box. questions. Choose the correct
dropdown box. questions. Choose the correct answer from each Consider the following project. Assume that all activities have the same non-zero slopes. Immediate Activity Normal Time (NT) Crash Time (CT) Predecessors A 8 6 B A 6 4 C 9 6 1. What is the shortest possible project duration? [ Select) 2. What duration should be assigned to activity C in order to complete the project in the shortest possible time at the lowest cost? [ Select)