Question: Question 1 2 pts This problem has TWO multiple choice questions. Choose the correct answer from each dropdown box. Consider the following project. Assume that

Question 1 2 pts This problem has TWO multiple

Question 1 2 pts This problem has TWO multiple choice questions. Choose the correct answer from each dropdown box. Consider the following project. Assume that all activities have the same slopes. Immediate Activity Normal Time (NT) Crash Time (CT) Predecessors A 23 15 B A 16 14 25 20 1. What is the shortest possible project duration? [ Select ] 2. What duration should be assigned to activity C in order to complete the project in the shortest possible time at the lowest cost? [ Select]