Question: Due to a technical issue, program migration (activity B) is delayed by 2 weeks . Will the project duration increase, decrease, or stay the same

Due to a technical issue, program migration (activity B) is delayed by 2 weeks. Will the project duration increase, decrease, or stay the same with this change? Explain.
Increase Decrease No change:
Explain:
Consider the following project for a company that is working to install a cloud-based ERP system (numbers indicate normal time in weeks). B:4 D:10 A:2 F:3 E:7 C:5Step by Step Solution