Question: With more ERP developers added to the project team, program auditing (activity D) is shortened by 2 weeks . Will the project duration increase, decrease,

With more ERP developers added to the project team, program auditing (activity D) is shortened by 2 weeks. Will the project duration increase, decrease, or stay the same with this change? Explain.
Increase Decrease No change:
Explain:
Consider the following project for a company that is working to install a cloud-based ERP system (numbers indicate normal time in weeks). B:4 D:10 A:2 F:3 E:7 C:5Step by Step Solution