Question: Dumfries Industries is generating a materials requirement plan for the next six weeks. Here is its most current information: Master Production Schedule: Week: 1 2

Dumfries Industries is generating a materials requirement plan for the next six weeks. Here is its most current information:

Master Production Schedule:

Week:

1

2

3

4

5

6

Item A

10

0

50

50

0

10

Other Information:

Item

Items Parent

Items Lead Time

Items Lot Size

Items Current On-hand Inventory

A

None

1 week

lot for lot

10

B

A

1 week

20

20

C

A

1 week

20

40

How many levels does a product structure for Dumfries item A have? Please enter a whole number only, for example, 5.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!