Question: Duration Cost Activity Normal Crash Normal Crash A 5 3 4 0 0 5 3 0 B 3 2 3 5 0 4 1 0

Duration Cost
Activity Normal Crash Normal Crash
A 53400530
B 32350410
C 7410201095
D 43525560
E 63825975
F 42610750
G 63430565
H 7412501415
I 42390450