Question: Duration Cost Tasks Normal Crash Predecessor Normal Crash Cost/Day a 4 2 start 100 150 b 7 6 a 70 100 c 9 6 a

Duration Cost
Tasks Normal Crash Predecessor Normal Crash Cost/Day
a 4 2 start 100 150
b 7 6 a 70 100
c 9 6 a 100 125
d 4 1 b 50 80

Using the information provided, the established project duration is [days]. The critical path is [letters]. To complete the project in 13 days, you would need to crash activity [letter], [duration] days for a cost of [amount].