Question: Duration Cost Tasks Normal Crash Predecessor Normal Crash Cost/Day a 4 2 start 100 150 b 7 6 a 70 100 c 9 6 a
| Duration | Cost | |||||
| Tasks | Normal | Crash | Predecessor | Normal | Crash | Cost/Day |
| a | 4 | 2 | start | 100 | 150 | |
| b | 7 | 6 | a | 70 | 100 | |
| c | 9 | 6 | a | 100 | 125 | |
| d | 4 | 1 | b | 50 | 80 | |
Using the information provided, the established project duration is [days]. The critical path is [letters]. To complete the project in 13 days, you would need to crash activity [letter], [duration] days for a cost of [amount].