Question: Given: The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram
Given: The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram for said project. All durations are in days, and all costs are in dollars. The network diagram for the project is also shown below. Activity Immediate Normal Normal Crash Crash Predecessor Duration Cost Duration Cost ABCDEFC 6 100 4 500 10 200 A 3 50 B.C 4 150 G DOW 4 250 7 200 E 2 50 02437- 10 200 300 150 450 200 100 A A
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
