Question: Duration ( Days ) Activity Optimistic ( T _ ( o ) ) Most Likely ( T _ ( m ) ) Pessimistic ( T

Duration (Days) Activity Optimistic (T_(o)) Most Likely (T_(m)) Pessimistic (T_(p)) W 469 E 61015 S 71115 T 122036 E 81014 R 458 N 5815. Activity durations of the WESTERN project are not certain.
Their durations are given in three different durations.
Optimistic, most likely, and pessimistic duration.
The weight for optimistic: most likely: pessimistic is 1:4:1.What is the expected duration of the WESTERN project?
 Duration (Days) Activity Optimistic (T_(o)) Most Likely (T_(m)) Pessimistic (T_(p)) W