Question: Duration of critical path path duration = __________? Select one: A. Latest finish time B. Critical time C. Path slack D. Latest start time The
Duration of critical path path duration = __________?
Select one:
A. Latest finish time
B. Critical time
C. Path slack
D. Latest start time
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
Select one:
True
False
The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:
Select one:
A. Pessimistic time
B. Optimistic time
C. Likeliest time
D. Utopian time
The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.
Select one:
True
False
The optimistic time is the amount of time the project will take under the worst-case scenario.
Select one:
True
False