Question: Duration Start Mode Task Name : 4 Conveyor Belt Project 0 days Thu 6/5 4 Hardware 0 days Thu 6/2 ? Hardware Specifications ?
Duration Start Mode Task Name : 4 Conveyor Belt Project 0 days Thu 6/5 4 Hardware 0 days Thu 6/2 ? Hardware Specifications ? Hardware Design ? Hardware Documentation ? Prototypes ? Order Circuit Boards ? Assemble Preproduction Models 4 Operating System 0 days Thu 6/ ? Kernel Specifications 4 Drivers 0 days Thu 6/5 ? Disk Drivers Serial I/Odrivers ?