Question: Duration (weeks) Activity A (start) B E F (end) 1 1 4 2 2 Precedes B, C E F F Crash Cost/Week $400 $100 $200

Duration (weeks) Activity A (start) B E F (end) 1

Duration (weeks) Activity A (start) B E F (end) 1 1 4 2 2 Precedes B, C E F F Crash Cost/Week $400 $100 $200 $300 $400 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (days) week(s) week(s) A B week(s)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!