Question: Activity Duration (weeks) A (start) B C E F (end) 3 2 5 2 3 Precedes Crash Cost/Week B, C E F $370 $120 $240
Suppose that Rafay is only given 9 wooks (instead of 11 ) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. The critical path is is the cheapest on the critical path to crash, so take it to 4 weeks. Now both paths through are critical. What is the cheapest way to crash the project to 9 weeks? Crash by 1 week. What is the total crashing cost? Total cost = Activity C's crash cost + Activity B's crash cost =(2)$240+(1)$120=$ (Enter your response as a whole number.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
