Question: During 2 0 2 3 , Cherry Corp. started a construction job with a total contract price of $ 1 , 0 5 0 ,

During 2023, Cherry Corp. started a construction job with a total contract price of $1,050,000. Cherry has used zero-profit method. The job was completed on December 15,2024. Additional data are as follows:
20232024
Actual costs incurred $405,000 $457,500
Estimated remaining costs 405,0000
Billings to date 360,000690,000
Collections to date 200,000480,000
For 2023, what amount should Cherry recognize as gross profit?
Question 37 Select one:
a.
$120,000
b.
$187,500
c.
$120,000
d.
$0