Question: During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job

During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job was completed on December 15, 2021. Additional data are as follows:

2020

2021

Actual costs incurred

$405,000

$457,000

Estimated remaining costs

405,000

Billings to date

360,000

690,000

Collections to date

200,000

480,000

For 2021, what amount should Bing recognize as gross profit?

$0

$120,000

$188,000

$142,500