Question: During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job
During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job was completed on December 15, 2021. Additional data are as follows:
| 2020 | 2021 | |||
| Actual costs incurred | $405,000 | $457,000 | ||
| Estimated remaining costs | 405,000 | |||
| Billings to date | 360,000 | 690,000 | ||
| Collections to date | 200,000 | 480,000 |
For 2021, what amount should Bing recognize as gross profit?
$0
$120,000
$188,000
$142,500