Question: During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2019. The following information is available.

During 2017, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2019. The following information is available.

2017

2018

2019

Costs incurred to date $366,300 $831,440 $1,067,000
Estimated costs to complete 623,700 262,560 0
Billings to date 297,000 894,000 1,590,000
Collections to date 270,000 816,000 1,417,000

a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit in 2017

Gross profit in 2018

Gross profit in 2019

b) Prepare all necessary journal entries for 2018.

Dr. Construction in Process

Cr. Materials, Cash, Payables

--

Dr. Accounts Receivable

Cr. Billings on Construction in Process

--

Dr. Cash

Cr. Accounts Receivable

--

Dr. Construction in Process

Dr. Construction Expense

Cr. Revenue from Long Term Contracts

c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

2017

2018

2019

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!