Question: During a project closing, problems with readiness or impact are evaluated. Which of the following project issues is an issue with impact? A . )
During a project closing, problems with readiness or impact are evaluated.
Which of the following project issues is an issue with impact?
A
The walking trails in the park were gravel, yet many local people prefer wellgroomed, paved trails.
B
The pump for the fountain in the main water feature is on back order.
C
The lights in the park shelter need to be connected to the electrical system.
D
The new playground equipment arrived to the site damaged.