Question: During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting
During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives. How should the project manager ensure that these changes are managed effectively? Record the changes using the risk register and continue monitoring. Review the project and communications management plan with the main stakeholder. Include the changes in the backlog and review priorities with the product owner. Deny the change requests and keep delivering the project as planned