Question: During Identify Stakeholder process, the project manager identifies all people or organizations impacted by the project, and documents relevant information regarding their interests, involvement, and

During Identify Stakeholder process, the project manager identifies all people or organizations impacted by the project, and documents relevant information regarding their interests, involvement, and impact on project success. In this context, all the following statements are true EXCEPT:
Question 6 options:
Stakeholders exert influence over the project and its deliverables.
It is critical for project success to identify the stakeholders early in the project.
All critical stakeholders should be engaged at the same time.
A strategy may be developed for approaching each stakeholder.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!