Question: During planning, your team has identified the items in the following table as work to be done on the project. All relationships re F-S relationships

During planning, your team has identified the items in the following table as work to be done on the project. All relationships re F-S relationships and duration are in weeks.

Task Duration Predecessor
A 1 Start
B 2 A
C 4 B
D 2 B
E 3 B
F 4 D,C
G 1 E
H 3 F
I 5 G
J 2 H,I

Now that all the previous changes have occurred (Task D changes to 3 weeks and task G changes to 4 weeks), how much longer will it take to finish the project with these changes?

Note - write duration only, For example - 7 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!