Question: During planning, your team has identified the items in the following table as work to be done on the project. All relationships re F-S relationships
During planning, your team has identified the items in the following table as work to be done on the project. All relationships re F-S relationships and duration are in weeks.
| Task | Duration | Predecessor |
| A | 1 | Start |
| B | 2 | A |
| C | 4 | B |
| D | 2 | B |
| E | 3 | B |
| F | 4 | D,C |
| G | 1 | E |
| H | 3 | F |
| I | 5 | G |
| J | 2 | H,I |
Now that all the previous changes have occurred (Task D changes to 3 weeks) and task G changes to 4 weeks), management asks you to cut the project duration by 2 weeks. Which of the following are viable options to do this?