Question: During project closure, a project manager performs a final inspection of all deliverables to verify that all work items the team committed to do are
During project closure, a project manager performs a final inspection of all deliverables to verify that all work items the team committed to do are complete and assigns ownership and target dates. Which of the following could best be used to accomplish this task?
Question Answer
a
transition plan
b
lessons learned
c
closeout report
d
punch list