Question: During project execution you found * out that work is often not performed at the right time and in the right order. Deliverables are made

During project execution you found * out that work is often not performed at the right time and in the right order. Deliverables are made by one team member that cannot be processed by another one. This already leads to timely rework and bad morale among team members. Which project management tool is most appropriate to deal with problem like this?

a. Organization chart

b. RACI matrix

c. Communication management plan

d. Work authorization system