Question: During project planning of a large, complex project, project management best practices were rigorously and thoroughly followed. During project execution, the project experienced several critical
During project planning of a large, complex project, project management best practices were rigorously and thoroughly followed. During project execution, the project experienced several critical risks, which were foreseen and previously identified. Despite the meticulous planning, the project failed to achieve the established objectives due to these realized risks.
What may have gone wrong in this scenario?
The risk responses were poorly devised
The realized risks had not been identified earlier in the project
There was little or no action taken to manage the known risks
The qualitative risk analysis was inadequate
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock