Question: During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery of critical tasks.How
During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery of critical tasks.How should the project manager address this situation?A Communicate the concerns to the project management office PMO during the weekly project reportsB. Call for a team meeting to decide if the changes should be includedC. Initiate the change request to modify the scope and adjust the timelinesD. Conduct an impact analysis and present the results to the steering committee for approval