Question: During the Operations and Maintenance gate review, it is determined that all portions of your project satisfied requirements and met operational needs, but only some


During the Operations and Maintenance gate review, it is determined that all portions of your project satisfied requirements and met operational needs, but only some continue to have available funding while others do not. What is the appropriate decision at this point? Develop a cheaper solution for the portion of the project that no longer has adequate funding Move the entire project into the Closeout phase Allow the portions of the project that no longer have funding to proceed to closeout and continue operations and maintenance on the portions that still have available funding Continue operations and maintenance on all portions of the project and share the available funds