Question: e ( Project management techniques: PERT and CPM , difficult ) { AACSB: Analytic Skills } A project whose critical path has an estimated time

e (Project management techniques: PERT and CPM, difficult){AACSB: Analytic Skills}
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day
a.98(rounded to nearest day).
b.112
c.120
d.124
e.220