Question: Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM. An architect has been awarded a contract to prepare

Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.

An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.

Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.

An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.

Job

Description

Predecessor

Expected time in days

A

Prepare preliminary sketches

NA

2

B

Outline specifications

NA

1

C

Prepare drawings

A

3

D

Write specifications

A B

2

E

Run prints

C D

1

F

Have specifications printed

B D

3

G

Assemble bid package

E F

1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!