Question: Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM. An architect has been awarded a contract to prepare
Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job | Description | Predecessor | Expected time in days |
A | Prepare preliminary sketches | NA | 2 |
B | Outline specifications | NA | 1 |
C | Prepare drawings | A | 3 |
D | Write specifications | A B | 2 |
E | Run prints | C D | 1 |
F | Have specifications printed | B D | 3 |
G | Assemble bid package | E F | 1 |