Question: e ) Using the Critical Ratio ( CR ) scheduling rule for sequencing the jobs, the order is: Part 3 0 Part 3 1 Part

e) Using the Critical Ratio(CR) scheduling rule for sequencing the jobs, the order is:
Part 30Part 31Part 32
Sequence
Job
1
D
2
C
3
A
4
B
Part 33
The average tardiness(job lateness) for the sequence developed using the CR rule=
enter your response here days (round your response to two decimal places).
.
.
.
Question content area right
Part 1
An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left:
Job
Due Date
Duration(days)
Upper A
212
6
Upper B
209
3
Upper C
208
3
Upper D
210
8
All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 205. Compute all times based on initiating work on day 205.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!