Question: E4-13 Determining job costs, using the ABC method Job 19AB required $10,000 for direct materials, $4,000 for direct labor, 300 direct labor hours, 150 machine

 E4-13 Determining job costs, using the ABC method Job 19AB required

E4-13 Determining job costs, using the ABC method Job 19AB required $10,000 for direct materials, $4,000 for direct labor, 300 direct labor hours, 150 machine hours, three material moves, and five component parts. The cost pools and overhead rates for each pool follow: Cost Pool Overhead Rate Direct labor support $10/direct labor hour Machining support $15/machine hour Material movement $350/material move Engineering $700/component part Determine the cost of Job 19AB using the ABC method