- Each of 8 jobs needs to go through work center A and B. Find the optimal sequence of jobs to minimize the makespan using Johnson's rule.
Processing Time in hours | ||||
Job | Work center A | Work center B | ||
A | 4.0 | 2.4 | ||
B | 7.4 | 5.9 | ||
C | 8.5 | 9.4 | ||
D | 1.7 | 3.0 | ||
E | 4.4 | 5.4 | ||
F | 2.5 | 6.6 | ||
G | 6.7 | 5.1 | ||
H | 5.6 | 0.9 |