Question: Eagle Corp. is considering two projects, Project A and Project B, with the following cash flows: Project A : Year Cash Flow ($) 0 -120,000
Eagle Corp. is considering two projects, Project A and Project B, with the following cash flows:
Project A:
Year | Cash Flow ($) |
0 | -120,000 |
1 | 30,000 |
2 | 50,000 |
3 | 70,000 |
4 | 80,000 |
Project B:
Year | Cash Flow ($) |
0 | -140,000 |
1 | 40,000 |
2 | 60,000 |
3 | 80,000 |
4 | 90,000 |
The discount rate for Project A is 8%, and for Project B, it is 10%.
a) i. Calculate the payback period for each project.
ii. Which project should be accepted if the payback period required is 3.5 years?
b) i. Calculate the Net Present Value (NPV) for each project.
ii. Which project should be accepted based on the NPV rule?
c) i. Calculate the Internal Rate of Return (IRR) for each project.
ii. Which project should be accepted based on the IRR rule?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
