Question: Earliest Finish Activity A Activity Time 2 1 Earliest Start 0 2 Latest Start 0 3 Latest Finish 2 4 5 Slack 0 1 0

Earliest Finish Activity A Activity Time 2 1

Earliest Finish Activity A Activity Time 2 1 Earliest Start 0 2 Latest Start 0 3 Latest Finish 2 4 5 Slack 0 1 0 B 3 5 3 7 2 3 2 4 D 10 11 E 3 5 8 11 3 F 5 11 5 11 0 G 4 11 15 11 15 0 Using the information shown in the table above, what is the project duration? O A 10 OB. 12 O C. 15 OD. 14