Question: Consider a project with the following activity list Activity Immediate Predecessors Estimated Duration (months) A ____ 1 B A 2 C B 4 D B
Consider a project with the following activity list
Activity | Immediate Predecessors | Estimated Duration (months) |
A | ____ | 1 |
B | A | 2 |
C | B | 4 |
D | B | 3 |
E | B | 2 |
F | C | 3 |
G | D,E | 5 |
H | F | 1 |
I | G,H | 4 |
J | I | 2 |
K | I | 3 |
L | J | 3 |
M | K | 5 |
N | L | 4 |
a. Construct the project network for this project.
b. Find the earliest start time and earliest finish time for each activity.
c. Find the latest start time and latest finish time for each activity.
d. Find the slack for each activity. Which of the paths is a critical path?
e. What is the critical path?
Step by Step Solution
3.45 Rating (148 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
63656da98ccc7_240159.pdf
180 KBs PDF File
63656da98ccc7_240159.docx
120 KBs Word File