Consider a project with the following activity list Activity Immediate Predecessors Estimated Duration (months) A ____ 1
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider a project with the following activity list
Activity | Immediate Predecessors | Estimated Duration (months) |
A | ____ | 1 |
B | A | 2 |
C | B | 4 |
D | B | 3 |
E | B | 2 |
F | C | 3 |
G | D,E | 5 |
H | F | 1 |
I | G,H | 4 |
J | I | 2 |
K | I | 3 |
L | J | 3 |
M | K | 5 |
N | L | 4 |
a. Construct the project network for this project.
b. Find the earliest start time and earliest finish time for each activity.
c. Find the latest start time and latest finish time for each activity.
d. Find the slack for each activity. Which of the paths is a critical path?
e. What is the critical path?
Related Book For
Principles of Corporate Finance
ISBN: 978-0077404895
10th Edition
Authors: Richard A. Brealey, Stewart C. Myers, Franklin Allen
Posted Date: