Question: EarliestLatestEarliestLatestStartStartFinishFinishSlackCriticalActivity ( ES ) ( LS ) ( EF ) ( LF ) ( LS ES ) Path ? A 0 0 5 5 0

EarliestLatestEarliestLatestStartStartFinishFinishSlackCriticalActivity(ES)(LS)(EF)(LF)(LSES)Path?A00550YesB048124C598124D596104E55660YesF6610100YesG101024240YesH81220244I242427270Yes
Suppose the project has been underway for eight weeks. Activities A and E have been completed. Activity F has commenced but has two weeks remaining. Activities C and D have not started yet. Activity B has two weeks remaining (it was not started until week 2). Update the activity schedule for the project. In particular, how has the slack for each activity changed? If your answer is zero enter 0.