Question: EarliestLatestEarliestLatestStartStartFinishFinishSlackCriticalActivity ( ES ) ( LS ) ( EF ) ( LF ) ( LS ES ) Path ? A 0 0 5 5 0
EarliestLatestEarliestLatestStartStartFinishFinishSlackCriticalActivityESLSEFLFLSESPathAYesBCDEYesFYesGYesHIYes
Suppose the project has been underway for eight weeks. Activities A and E have been completed. Activity F has commenced but has two weeks remaining. Activities C and D have not started yet. Activity B has two weeks remaining it was not started until week Update the activity schedule for the project. In particular, how has the slack for each activity changed? If your answer is zero enter