Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.
A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks. Activity Precedence Activities Activity Time (weeks) ES LS EF LF Slack Critical Path? A B C D E F G H I Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?

Start Activity A B D E F G H A 5 8 B D 4 12 Precedence Activity Activities Time (weeks) ES F 10 LS G EF Finish Critical LF Slack Path?
Step by Step Solution
3.28 Rating (145 Votes )
There are 3 Steps involved in it
To solve this problem well perform a forward pass and a backward pass to determine the early start ES late start LS early finish EF and late finish LF ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
6090e5480c781_21999.pdf
180 KBs PDF File
6090e5480c781_21999.docx
120 KBs Word File