Question: A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.

A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks. Activity Precedence Activities Activity Time (weeks) ES LS EF LF Slack Critical Path? A B C D E F G H I Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?

A project network is shown below. Use a forward an

Start Activity A B D E F G H A 5 8 B D 4 12 Precedence Activity Activities Time (weeks) ES F 10 LS G EF Finish Critical LF Slack Path?

Step by Step Solution

3.28 Rating (145 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this problem well perform a forward pass and a backward pass to determine the early start ES late start LS early finish EF and late finish LF ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

6090e5480c781_21999.pdf

180 KBs PDF File

Word file Icon

6090e5480c781_21999.docx

120 KBs Word File

Students Have Also Explored These Related Computer Network Questions!