Question: Earned Value ( 2 0 points ) Assume you are the project manager and based o n your customers' requirements you have determined there are

Earned Value (20 points)
Assume you are the project manager and based on your customers' requirements you have
determined there are four main tasks in a Dream Kitchen project. Each phase has been assigned a
TBC. Specifically, the customer wants their existing kitchen cabinets and appliances removed, a
wall separating the kitchen from the living area removed, and a support beam installed (Task1-
$25,000); plumbing, electrical, and mechanical installedrelocated (Task2- $16,000); new
appliances, cabinets, and countertops (Task3- $35,000); and paint, trim, and clean up(Task4-
$3,000). You estimate this will take 5 weeks to complete.
The budgeted costs are as follows:
Assume 4 weeks have passed and these are the actual costs per week:
Below is the cumulative percentage of work complete per task per week:
Show calculations and complete the table with the calculated valuesanswers asof the end of week 4
(20 points):
 Earned Value (20 points) Assume you are the project manager and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!