Question: 1 . Earned Value ( 2 0 points ) * Assume you are the project manager and based o n your customers requirements you have
Earned Value points
Assume you are the project manager and based your customers requirements you have determined there are four main tasks a Dream Kitchen project. Each phase has been assigned a Specifically, the customer wants their existing kitchen cabinets and appliances removed, a wall separating the kitchen from the living area removed, and a support beam installed $; plumbing, electrical, and mechanical installeelocated $; new appliances, cabinets, and countertops $; and paint, trim, and clean $ You estimate this will take weeks complete.
The budgeted costs are follows:
Budgeted Per Week
Task
Task
Task
Task
Assume weeks have passed and these are the actual costs per week:
Actual Costs Per Week
Task
Task
Task
Task
Below the cumulative percentage work complete per task per week:
Cumulative Percentage Complete
Task
Task
Task
Task
Show calculations and complete the table with the calculated valuenswers the end week points:
Calculations
point
point
CAC point
CEV point
CPI point
point
SPI point
point
Final Duration
Planned Duratio
points
FCAC Method
points
FCAC Method
CAC CEV
points
this project over under budget?
point
this project ahead, time, behind schedule?
point
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
