Question: 1 . Earned Value ( 2 0 points ) * Assume you are the project manager and based o n your customers requirements you have

1. Earned Value (20 points)
* Assume you are the project manager and based on your customers requirements you have determined there are four main tasks in a Dream Kitchen project. Each phase has been assigned a TBC. Specifically, the customer wants their existing kitchen cabinets and appliances removed, a wall separating the kitchen from the living area removed, and a support beam installed (Task1- $25,000); plumbing, electrical, and mechanical installedrelocated (Task2- $16,000); new appliances, cabinets, and countertops (Task3- $35,000); and paint, trim, and clean up(Task4- $3,000). You estimate this will take 5 weeks to complete.
* The budgeted costs are as follows:
Budgeted Per Week (in000s)
TBC12345
Task 1256127
Task 21621031
Task 335216107
Task 4312
* Assume 4 weeks have passed and these are the actual costs per week:
Actual Costs Per Week (in000s)
1234
Task 15165
Task 22582
Task 351810
Task 42
* Below is the cumulative percentage of work complete per task per week:
Cumulative Percentage Complete
1234
Task 130%82%100%
Task 215%25%75%95%
Task 312%35%75%
Task 450%
Show calculations and complete the table with the calculated valuesanswers asof the end of week 4(20 points):
Calculations
TBC(1 point)
CBC(1 point)
CAC (1 point)
CEV (4 point)
CPI (2 point)
CV(1 point)
SPI (1 point)
SV(1 point)
Final Duration
(calculateas Planned DurationSPI)
(2 points)
FCAC Method 1
(calculateasTBCCPI)
(2 points)
FCAC Method 2
CAC +(TBC- CEV)
(2 points)
Is this project over or under budget?
(1 point)
Is this project ahead, on-time, or behind schedule?
(1 point)
 1. Earned Value (20 points) * Assume you are the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!