Question: EARNED VALUE ANALYSIS * end of 6th week WEEK Planned Value* RP Earned Value ACTIVITY 1 2 3 4 5 6 7 8 9 10
EARNED VALUE ANALYSIS * end of 6th week WEEK Planned Value* RP Earned Value ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 Initial meeting with project sponsors $15,000 $15,000 100% Draft project requirements $23,000 $9,000 $32,000 100% Review with stakeholders $4,000 $8,000 $12,000 100% Develop and approve project charter $9,000 $9,000 100% Develop WBS $12,000 $12,000 100% Estimate durations $13,000 $13,000 100% Assign resources $8,000 $8,000 $4,000 $16,000 75% Determine task relationships $8,000 $8,000 50% Enter cost information $16,000 $16,000 25% Review plan with stakeholders $8,000 $0 0 Review off-the-shelf training materials $23,000 $0 0 Negotiate contract for materials $24,000 $16,000 $0 0 Develop communications for new training $18,000 $0 0 Create survey to determine needs $24,000 $0 0 Administer survey $12,000 $0 0 Develop list of training instructors $6,000 $12,000 $0 0 Setup classrooms $30,000 $30,000 $0 0 Schedule courses $4,000 $2,000 $8,000 $0 0 Develop system for signing up for classes $16,000 $0 0 Develop course evaluation form $20,000 $0 0 BAC (total budget for the project) Weekly Planned Value (PV) Cumulative Planned Value (PV) Weekly Actual Cost (AC) $17,000 $25,000 $13,000 $30,000 $46,000 $9,000 Cumulative Actual Cost (AC) Weekly Earned Value (EV) Cumulative Earned Value (EV) Project EV as of Week 6 Project PV as of Week 6 Project AC as of Week 6 CV = EV - AC SV = EV - PV CPI = EV/AC SPI = EV/PV Estimate At Completion (EAC)=BAC/CPI Estimated Time to Complete=OTE/SPI weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
