Question: Earned value analysis (EVA) is built on many assumptions. One limitation of EVA is that it is frequently based on the assumption that resource utilization
Earned value analysis (EVA) is built on many assumptions. One limitation of EVA is that it is frequently based on the assumption that resource utilization is ______ throughout the life of a task, which is not always realistic.
A. uniform
B. variable
C. unreliable
D. sporadic