Question: Earned value analysis is the project management tool used to measure project progress. (a) Based on the figure given, analyse the project using all information

Earned value analysis is the project management

Earned value analysis is the project management tool used to measure project progress. (a) Based on the figure given, analyse the project using all information given in the graph. 75 75 Status Date PV 50 -50 $'s 35 SV = -20 AC $'s CV=-5 25 25 EV CPI = 30/35 = 0.86 SPI = 30/50 = 0.60 0 Time 6 12 18 24