Question: Earned value analysis is the project management tool used to measure project progress. (a) Based on the figure given, analyse the project using all information

Earned value analysis is the project management

Earned value analysis is the project management tool used to measure project progress. (a) Based on the figure given, analyse the project using all information given in the graph. 75 175 Status Date PV 50+ -50 $'s 35 30 AC SV = - 20 $'s CV=-5 25 -25 EV CPI = 30/35 = 0.86 SPI = 30/50 = 0.60 0 Time 6 12 18 24

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!