Question: Earned Value Analysis table [ [ , Week ] , [ , 1 , 2 , 3 , 4 , 5 , 6 ,
Earned Value Analysis
tableWeekTask A workerhoursTask,wohour,,,,aTask C workerhourstableWeekly ScheduledWorkerHourstableCumulative ScheduledWorkerHours BCWS
Assume that we have worked on this project for weeks. At the end of each week, we have scheduled a review meeting and estimated the percentage of work completed on each task.
Based on these reports, please calculate:
a ACWP
b BCWP
c
d
e SI
f
Note. BCWS budgeted cost of work scheduled.
Cumulative Percentage of Work Completed at the End of Each Week
tableWeekTask A
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
